Coordinating the Design
Month five is where a good concept either holds its nerve or slowly gets watered down.
So far in this series we've set out a brief, a budget and a site appraisal, secured your site, put your design team in place and, last month, developed your concept design. This month is about testing that concept and proving it works. In the RIBA Plan of Work, the framework most architects in the UK use to run a project, this is Stage 3: Spatial Coordination. Your design team checks the concept against the engineering, so that every system needed to build and run your home is accounted for, and fits, before the detailed information to manufacture and build it is produced in the months ahead.
It's also the month you open proper talks with your planning authority, ready for your application next month. Here's how I'd approach it, in five steps and one conversation.
Step one: coordinate, don't compromise
The key skill this month is coordination without compromise. Structure, services, Passivhaus performance and cost all have to come together, and each of them pulls the design in its own direction.
The risk is that each discipline designs in its own silo. A beam that needs a deeper floor here. A duct that wants to cut through a wall there. Each fix looks small on its own, and each one can be justified on its own terms. But bit by bit, the original concept is eroded, and the home you fell in love with in Month 04 quietly becomes something else.
The answer is teamwork: regular, open and transparent design team meetings, where problems are solved together and the concept is respected. As your architect, that's a big part of my job this month, keeping everyone pulling in the same direction. And to be clear, this is refinement, not radical change. If the concept was right last month, it should still be recognisable at the end of this one.
Step two: refine with the market
Your design studies should now run alongside cost exercises and an outline specification. That specification covers the key systems of the build: foundations, superstructure, external walls and roof. It doesn't need every detail yet, but it does need enough to price.
This is also the time to talk to the people who'll make and build the big-ticket items:
· groundworks contractors
· timber frame kit suppliers
· window and door manufacturers
· roofers
Early conversations test the design against how things are actually made, and they give you real numbers rather than rates from a book. That goes a long way to keeping your budget under control.
It may take a few rounds to get the cost plan and your budget aligned. That's perfectly normal. Far better to have those rounds now, on paper, than later, on site. The test for every change is the same: does it still deliver the brief you agreed?
Step three: make it fit
Next comes technical coordination. Your structural engineer, services engineer and any other consultants make sure every technical aspect is covered and that the systems physically fit together: the structure, the ventilation routes, the pipework and the cables, all inside a building envelope that has to stay airtight and well insulated.
It's good practice to run a building regulations check at this stage, or Building Standards if you're in Scotland, especially for anything that affects the layout, like stairs, escape routes or accessibility. Picking that up now avoids redesign later.
For Passivhaus, this is where the design is tested and optimised thoroughly in PHPP, the Passive House Planning Package. In Month 04 we used it to compare options with early assumptions. Now it runs with real build-ups, real window specifications and real ventilation routes. And I'd recommend bringing in your Passivhaus certifier for an early review, so you know you're on track before the details are drawn.
Step four: spend on the fabric first
With a coordinated design, your quantity surveyor can update the cost plan with a more detailed breakdown based on the Stage 3 design. It's the right moment to look hard at where the money is going.
My advice here is simple: spend on the fabric first. The structure, insulation, airtightness and windows are what give you comfort and low running costs for the life of your home. Expensive finishes can be changed later, and often add little to its long-term value. The walls, the windows and the airtightness layer are with you for good.
Passivhaus components can be expensive too, so make sure each one earns its place and delivers the energy savings you're looking for. Fabric first doesn't mean everything first.
Step five: approve, then build on it
Then it's over to you. Review the coordinated design with your architect, give your feedback, and approve it before moving on to Stage 4, Technical Design.
This sign-off really matters. Radical changes after this point are expensive and slow, because every consultant and supplier is about to build their own detailed information on top of it.
The milestones for Month 05 are:
1. A Stage 3 Spatial Coordination report
2. A Stage 3 cost plan
3. An early design review from your Passivhaus certifier
A spatially coordinated design means each designer, and each specialist supplier, can finalise their information in the next stage with only minor tweaks, not another major round of redesign.
The conversation: open talks with your planners
Finally, open talks with your local planning authority. In Month 04 you made a first enquiry. Now you have a coordinated design to show them. Arrange a pre-application meeting if your council offers one, present the design and ask for feedback on any concerns.
Go in prepared. Know your local plan and the policies that apply to your site, including any that support energy-efficient homes. Highlight your Passivhaus approach: local plans increasingly push for low-energy homes, so explain how your design delivers that.
If concerns are raised, work with your architect to adjust the design in a considered way. But you don't have to accept every view. If you have a robust, reasoned case for your proposals, the planning authority has to assess it fairly against its own policies. For Passivhaus, bring the evidence: the energy and environmental performance that justifies your design decisions.
Where Month 05 leaves you
By the end of month five, you'll have a coordinated design, a cost plan tested against the market, and an open dialogue with your planning authority. You'll know how your design responds to local policy, and you'll be ready to apply.
Next month, Month 06, we'll take you through the planning application itself, and we'll be halfway there.
If you're weighing up budget and process before you start, our free Investment Guide sets out how we work: https://www.novo-design.co.uk/investmentguide-1. And if you'd like to talk about your own project, you can reach us at https://www.novo-design.co.uk/contact.
Design with care. Live well.